Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
30 | Complete Transition to New Controls W/O Beam | Biocca | 0 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
30 | Complete Transition to New Controls W/O Beam | Timossi | 0 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
30 | Complete Transition to New Controls W/O Beam | Steier | 0 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
40 | Good Vacuum W/O Beam (Sublimate early enough) | Colomb | 0 hrs | Sun 4/28/02 | Sun 4/28/02 | 0% |
40 | Good Vacuum W/O Beam (Sublimate early enough) | Operators | 0 hrs | Sun 4/28/02 | Sun 4/28/02 | 0% |
81 | First Stored Beam in SR | Steier | 0 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
86 | Decision Point for Control System (revert to ILCs ?) | Biocca | 0 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
86 | Decision Point for Control System (revert to ILCs ?) | Steier | 0 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
86 | Decision Point for Control System (revert to ILCs ?) | Robin | 0 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
50 | DCCT | Physics | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
51 | Scrapers | Physics | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
52 | Tune Measurement System | Physics | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
53 | RF Frequency | Physics | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
55 | Shunts | Physics | 0.5 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
57 | Stability | Physics | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
58 | SP-AM | Physics | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
60 | Ramping | Physics | 2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
59 | Data Rates | Physics | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
61 | Check Power Supply Can Reach Max/Min Current | Physics | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
102 | Find QF and QD Centers | Physics | 6 hrs | Fri 5/3/02 | Sat 5/4/02 | 100% |
102 | Find QF and QD Centers | Operators | 6 hrs | Fri 5/3/02 | Sat 5/4/02 | 100% |
78 | Measurement Of Orbit Jitter | Steier | 1.5 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
78 | Measurement Of Orbit Jitter | Scarvie | 1.5 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
78 | Measurement Of Orbit Jitter | Nadolski | 1.5 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
77 | Response Matrix Measured | Steier | 0.75 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
77 | Response Matrix Measured | Scarvie | 0.75 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
77 | Response Matrix Measured | Nadolski | 0.75 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
79 | Test Ramping with new controls | Steier | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
79 | Test Ramping with new controls | Scarvie | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
79 | Test Ramping with new controls | Nadolski | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
106 | Study transverse multibunch feedbacks with HOM dampers | Barry | 3.65 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
98 | Prepare For/Test Beam Based Alignment | Scarvie | 2 hrs | Fri 5/3/02 | Fri 5/3/02 | 100% |
103 | Find QFA+QDA Centers | Physics | 5 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
103 | Find QFA+QDA Centers | Operators | 5 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
104 | Establish Golden Orbit Without User Bumps | Physics | 2 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
104 | Establish Golden Orbit Without User Bumps | Operators | 2 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
105 | Measure Response Matrix again | Physics | 1 hr | Sat 5/4/02 | Sat 5/4/02 | 100% |
105 | Measure Response Matrix again | Operators | 1 hr | Sat 5/4/02 | Sat 5/4/02 | 100% |
108 | Fit Lattice Model | Steier | 8 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
108 | Fit Lattice Model | Nadolski | 8 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
109 | Generate Feed Forward Tables | Physics | 8 hrs | Sat 5/4/02 | Sun 5/5/02 | 100% |
109 | Generate Feed Forward Tables | Operators | 8 hrs | Sat 5/4/02 | Sun 5/5/02 | 100% |
66 | Correct first turn orbit | Steier | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
66 | Correct first turn orbit | Scarvie | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
66 | Correct first turn orbit | Nadolski | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
67 | Adjust tunes/lattice | Steier | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
67 | Adjust tunes/lattice | Scarvie | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
67 | Adjust tunes/lattice | Nadolski | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
68 | Tune rf phase - relative energy | Steier | 0.5 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
68 | Tune rf phase - relative energy | Byrne | 0.5 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
37 | Follow comprehensive startup procedure (Storage Ring) | Operators | 32 hrs | Sat 4/27/02 | Sat 4/27/02 | 100% |
34 | Finish all shutdown work | Harkins | 0 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
71 | Check BPMs Calibrate | Steier | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
71 | Check BPMs Calibrate | Scarvie | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
71 | Check BPMs Calibrate | Nadolski | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
72 | Check Sample Rates | Steier | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
72 | Check Sample Rates | Scarvie | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
72 | Check Sample Rates | Nadolski | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
73 | Measure Noise | Steier | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
73 | Measure Noise | Scarvie | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
73 | Measure Noise | Nadolski | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
74 | Tune Measurement | Steier | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
74 | Tune Measurement | Scarvie | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
74 | Tune Measurement | Nadolski | 0.2 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
75 | RF Frequency | Steier | 0.1 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
75 | RF Frequency | Scarvie | 0.1 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
75 | RF Frequency | Nadolski | 0.1 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
76 | Quick setup (orbit, tune, chrom correction) | Steier | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
76 | Quick setup (orbit, tune, chrom correction) | Scarvie | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
76 | Quick setup (orbit, tune, chrom correction) | Nadolski | 1 hr | Tue 4/30/02 | Tue 4/30/02 | 100% |
84 | Analyze response matrix | Steier | 0 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
84 | Analyze response matrix | Nadolski | 0 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
82 | Scrub With Beam (1.9 GeV) -> maybe more time needed ? Vacuumwork in sector 11 ? | Operators | 6 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
65 | Watch temperatures of HOM dampers -> do not overfill ring | Kwiatkowski | 10 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
65 | Watch temperatures of HOM dampers -> do not overfill ring | Julian | 10 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
65 | Watch temperatures of HOM dampers -> do not overfill ring | Baptiste | 10 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
65 | Watch temperatures of HOM dampers -> do not overfill ring | Physics | 10 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
65 | Watch temperatures of HOM dampers -> do not overfill ring | Operators | 10 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
83 | During Scrubbing: Test Slow Orbit Feedback (with extended precision DACs) | Steier | 6 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
83 | During Scrubbing: Test Slow Orbit Feedback (with extended precision DACs) | Scarvie | 6 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
131 | Evaluate Overall Beam Stability/Quality with Beamlines | Byrne | 2 hrs | Tue 5/7/02 | Tue 5/7/02 | 100% |
131 | Evaluate Overall Beam Stability/Quality with Beamlines | Beamlines | 2 hrs | Tue 5/7/02 | Tue 5/7/02 | 100% |
131 | Evaluate Overall Beam Stability/Quality with Beamlines | Byrd | 2 hrs | Tue 5/7/02 | Tue 5/7/02 | 100% |
131 | Evaluate Overall Beam Stability/Quality with Beamlines | Steier | 2 hrs | Tue 5/7/02 | Tue 5/7/02 | 100% |
133 | Align (potentially frontends) | Byrne | 12 hrs | Tue 5/7/02 | Wed 5/8/02 | 0% |
133 | Align (potentially frontends) | Duarte | 12 hrs | Tue 5/7/02 | Wed 5/8/02 | 0% |
133 | Align (potentially frontends) | Beamlines | 12 hrs | Tue 5/7/02 | Wed 5/8/02 | 0% |
90 | EPBI Test 2 | Byrne | 4 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
90 | EPBI Test 2 | Operators | 4 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
20 | Check PCI controls of quadrupole supplies | Biocca | 72 hrs | Mon 4/15/02 | Thu 4/18/02 | 100% |
20 | Check PCI controls of quadrupole supplies | Timossi | 72 hrs | Mon 4/15/02 | Thu 4/18/02 | 100% |
20 | Check PCI controls of quadrupole supplies | Scarvie | 36 hrs | Mon 4/15/02 | Thu 4/18/02 | 100% |
20 | Check PCI controls of quadrupole supplies | Steier | 72 hrs | Mon 4/15/02 | Thu 4/18/02 | 100% |
15 | Check all extended precision DAC boards | Biocca | 48 hrs | Wed 4/10/02 | Fri 4/12/02 | 100% |
15 | Check all extended precision DAC boards | Timossi | 48 hrs | Wed 4/10/02 | Fri 4/12/02 | 100% |
15 | Check all extended precision DAC boards | Jacobson | 48 hrs | Wed 4/10/02 | Fri 4/12/02 | 100% |
15 | Check all extended precision DAC boards | Scarvie | 48 hrs | Wed 4/10/02 | Fri 4/12/02 | 100% |
15 | Check all extended precision DAC boards | Steier | 48 hrs | Wed 4/10/02 | Fri 4/12/02 | 100% |
2 | Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...) | Byrd | 0 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
2 | Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...) | Barry | 0 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
2 | Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...) | Stover | 0 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
2 | Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...) | Kwiatkowski | 0 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
16 | Measure open loop transferfunctions of fast FB … deferred | Jacobson | 72 hrs | Fri 4/12/02 | Mon 4/15/02 | 0% |
16 | Measure open loop transferfunctions of fast FB … deferred | Steier | 72 hrs | Fri 4/12/02 | Mon 4/15/02 | 0% |
16 | Measure open loop transferfunctions of fast FB … deferred | Domning | 72 hrs | Fri 4/12/02 | Mon 4/15/02 | 0% |
16 | Measure open loop transferfunctions of fast FB … deferred | Scarvie | 72 hrs | Fri 4/12/02 | Mon 4/15/02 | 0% |
11 | Software summing junctions (QF,QD) … deferred | Scarvie | 12 hrs | Fri 4/5/02 | Sat 4/6/02 | 75% |
11 | Software summing junctions (QF,QD) … deferred | Steier | 12 hrs | Fri 4/5/02 | Sat 4/6/02 | 75% |
143 | Frontends/inside tunnel | Duarte | 480 hrs | Wed 4/3/02 | Tue 4/23/02 | 100% |
143 | Frontends/inside tunnel | Byrne | 480 hrs | Wed 4/3/02 | Tue 4/23/02 | 100% |
143 | Frontends/inside tunnel | deMarco | 480 hrs | Wed 4/3/02 | Tue 4/23/02 | 100% |
144 | Outside tunnel | Duarte | 192 hrs | Tue 4/23/02 | Wed 5/1/02 | 100% |
144 | Outside tunnel | deMarco | 192 hrs | Tue 4/23/02 | Wed 5/1/02 | 100% |
144 | Outside tunnel | Beamlines | 192 hrs | Tue 4/23/02 | Wed 5/1/02 | 100% |
145 | Final optimization | Beamlines | 48 hrs | Tue 5/7/02 | Thu 5/9/02 | 20% |
99 | Check 3 HC Settings with HOM dampers | Byrd | 4 hrs | Fri 5/3/02 | Fri 5/3/02 | 100% |
99 | Check 3 HC Settings with HOM dampers | deSantis | 4 hrs | Fri 5/3/02 | Fri 5/3/02 | 100% |
35 | Search and secure LINAC, booster + SR | Operators | 4 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
38 | Setup Beam Thru Injector and BTS Line | Byrne | 16 hrs | Sun 4/28/02 | Mon 4/29/02 | 100% |
54 | BPM and IDBPM data rates (no beam) | Physics | 0.25 hrs | Tue 4/30/02 | Tue 4/30/02 | 100% |
100 | Study Longitudinal Multibunch Feedback with HOM dampers | Stover | 8 hrs | Fri 5/3/02 | Fri 5/3/02 | 100% |
122 | Coupling Studies | Nadolski | 7 hrs | Tue 5/7/02 | Tue 5/7/02 | 100% |
124 | Improve tune feed forward | Steier | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
124 | Improve tune feed forward | Scarvie | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
123 | Incorporate tune feed forward into FF table generation | Steier | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
123 | Incorporate tune feed forward into FF table generation | Scarvie | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
110 | Test Routine high current operation | Physics | 4 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
110 | Test Routine high current operation | Operators | 4 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
110 | Test Routine high current operation | Byrne | 2 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
110 | Test Routine high current operation | Byrd | 4 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
119 | Initial tests with fast orbit feedback I | Steier | 8 hrs | Sun 5/5/02 | Mon 5/6/02 | 0% |
119 | Initial tests with fast orbit feedback I | Jacobson | 8 hrs | Sun 5/5/02 | Mon 5/6/02 | 0% |
119 | Initial tests with fast orbit feedback I | Domning | 8 hrs | Sun 5/5/02 | Mon 5/6/02 | 0% |
119 | Initial tests with fast orbit feedback I | Scarvie | 8 hrs | Sun 5/5/02 | Mon 5/6/02 | 0% |
119 | Initial tests with fast orbit feedback I | Nadolski | 8 hrs | Sun 5/5/02 | Mon 5/6/02 | 0% |
120 | Scan all small gap vacuum chambers for lifetime changes | Physics | 8 hrs | Mon 5/6/02 | Mon 5/6/02 | 0% |
120 | Scan all small gap vacuum chambers for lifetime changes | Operators | 8 hrs | Mon 5/6/02 | Mon 5/6/02 | 0% |
31 | Control System 100% Functional | Biocca | 0 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
31 | Control System 100% Functional | Steier | 0 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
17 | Superbends ready for startup | Calais | 0 hrs | Mon 4/22/02 | Mon 4/22/02 | 100% |
18 | Check out thermal behaviour of Superbends | Calais | 48 hrs | Mon 4/22/02 | Wed 4/24/02 | 100% |
18 | Check out thermal behaviour of Superbends | Bish | 48 hrs | Mon 4/22/02 | Wed 4/24/02 | 100% |
18 | Check out thermal behaviour of Superbends | Zbasnik | 48 hrs | Mon 4/22/02 | Wed 4/24/02 | 100% |
18 | Check out thermal behaviour of Superbends | Steier | 48 hrs | Mon 4/22/02 | Wed 4/24/02 | 100% |
19 | Check out Superbend ramping with new coldheads | Zbasnik | 24 hrs | Wed 4/24/02 | Thu 4/25/02 | 100% |
19 | Check out Superbend ramping with new coldheads | Steier | 24 hrs | Wed 4/24/02 | Thu 4/25/02 | 100% |
12 | normal precision IP boards replaced (ADC drift problem correctors) | Biocca | 0 hrs | Tue 4/9/02 | Tue 4/9/02 | 100% |
12 | normal precision IP boards replaced (ADC drift problem correctors) | Chin | 0 hrs | Tue 4/9/02 | Tue 4/9/02 | 100% |
12 | normal precision IP boards replaced (ADC drift problem correctors) | Webber | 0 hrs | Tue 4/9/02 | Tue 4/9/02 | 100% |
113 | HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 days | Byrd | 0 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
113 | HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 days | Kwiatkowski | 0 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
113 | HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 days | Robin | 0 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
113 | HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 days | Steier | 0 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
140 | Return to user operation | Byrne | 8 hrs | Thu 5/9/02 | Thu 5/9/02 | 0% |
140 | Return to user operation | Steier | 8 hrs | Thu 5/9/02 | Thu 5/9/02 | 0% |
140 | Return to user operation | Robin | 8 hrs | Thu 5/9/02 | Thu 5/9/02 | 0% |
89 | Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures) | Kwiatkowski | 12 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
89 | Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures) | Byrd | 12 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
89 | Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures) | Barry | 12 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
89 | Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures) | Stover | 12 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
36 | Follow comprehensive startup procedure (Linac+booster) | Operators | 16 hrs | Fri 4/26/02 | Sat 4/27/02 | 100% |
27 | Chicanes installed and ready for testing | Marks | 0 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
28 | Test chicane controls (especially sector 4) | Biocca | 8 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
28 | Test chicane controls (especially sector 4) | Timossi | 8 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
28 | Test chicane controls (especially sector 4) | Robb | 8 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
28 | Test chicane controls (especially sector 4) | Scarvie | 8 hrs | Fri 4/26/02 | Fri 4/26/02 | 100% |
29 | EPU in sector 11 installed and ready for testing | Marks | 0 hrs | Tue 4/23/02 | Tue 4/23/02 | 100% |
21 | New scrapers installed in sector 3 | Thur | 0 hrs | Mon 4/15/02 | Mon 4/15/02 | 100% |
22 | Test scraper controls | Thur | 72 hrs | Tue 4/16/02 | Fri 4/19/02 | 100% |
22 | Test scraper controls | Scarvie | 36 hrs | Tue 4/16/02 | Fri 4/19/02 | 100% |
24 | Develop schedule for potential removal … | Kwiatkowski | 120 hrs | Tue 4/9/02 | Sun 4/14/02 | 100% |
24 | Develop schedule for potential removal … | Plate | 120 hrs | Tue 4/9/02 | Sun 4/14/02 | 100% |
24 | Develop schedule for potential removal … | Colomb | 120 hrs | Tue 4/9/02 | Sun 4/14/02 | 100% |
24 | Develop schedule for potential removal … | Julian | 120 hrs | Tue 4/9/02 | Sun 4/14/02 | 100% |
25 | High power tests (vacuum conditioning) of HOM dampers | Kwiatkowski | 72 hrs | Thu 4/18/02 | Sun 4/21/02 | 100% |
26 | Test control room displays for HOM dampers | Timossi | 24 hrs | Thu 4/18/02 | Fri 4/19/02 | 100% |
26 | Test control room displays for HOM dampers | McDonald | 24 hrs | Thu 4/18/02 | Fri 4/19/02 | 100% |
26 | Test control room displays for HOM dampers | Scarvie | 12 hrs | Thu 4/18/02 | Fri 4/19/02 | 100% |
13 | Extended precision DAC boards installed | Biocca | 0 hrs | Tue 4/9/02 | Tue 4/9/02 | 100% |
13 | Extended precision DAC boards installed | Chin | 0 hrs | Tue 4/9/02 | Tue 4/9/02 | 100% |
14 | Check all normal precision IP boards | Biocca | 24 hrs | Tue 4/9/02 | Wed 4/10/02 | 100% |
14 | Check all normal precision IP boards | Timossi | 24 hrs | Tue 4/9/02 | Wed 4/10/02 | 100% |
14 | Check all normal precision IP boards | Scarvie | 24 hrs | Tue 4/9/02 | Wed 4/10/02 | 100% |
14 | Check all normal precision IP boards | Steier | 24 hrs | Tue 4/9/02 | Wed 4/10/02 | 100% |
135 | Fine Tune Beamline Alignment / Routine Operation | Byrne | 20 hrs | Wed 5/8/02 | Thu 5/9/02 | 0% |
135 | Fine Tune Beamline Alignment / Routine Operation | Duarte | 20 hrs | Wed 5/8/02 | Thu 5/9/02 | 0% |
135 | Fine Tune Beamline Alignment / Routine Operation | Beamlines | 20 hrs | Wed 5/8/02 | Thu 5/9/02 | 0% |
97 | Measure absolute orbits/coupling | Nishimura | 2 hrs | Fri 5/3/02 | Fri 5/3/02 | 100% |
97 | Measure absolute orbits/coupling | Nadolski | 2 hrs | Fri 5/3/02 | Fri 5/3/02 | 100% |
92 | Monitor radiation levels at new location | Fairchild | 2 hrs | Wed 5/1/02 | Thu 5/2/02 | 100% |
93 | Scan aperture in straight 11 (beam bumps+scraper scans) | Physics | 6 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
93 | Scan aperture in straight 11 (beam bumps+scraper scans) | Operators | 6 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
95 | Test chicane magnets in sector 4+11 | Physics | 4 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
95 | Test chicane magnets in sector 4+11 | Operators | 4 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
96 | Measure influence of EPU in sector 11 on beam | Physics | 4 hrs | Thu 5/2/02 | Fri 5/3/02 | 100% |
96 | Measure influence of EPU in sector 11 on beam | Operators | 4 hrs | Thu 5/2/02 | Fri 5/3/02 | 100% |
114 | HOM dampers decision point #2 (revert back) -> requires 1 day | Byrd | 0 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
114 | HOM dampers decision point #2 (revert back) -> requires 1 day | Kwiatkowski | 0 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
114 | HOM dampers decision point #2 (revert back) -> requires 1 day | Robin | 0 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
114 | HOM dampers decision point #2 (revert back) -> requires 1 day | Steier | 0 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
94 | Test of HOM dampers 2 (different fill patterns and currents) | Kwiatkowski | 12 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
94 | Test of HOM dampers 2 (different fill patterns and currents) | Byrd | 12 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
94 | Test of HOM dampers 2 (different fill patterns and currents) | Barry | 12 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
94 | Test of HOM dampers 2 (different fill patterns and currents) | Stover | 12 hrs | Thu 5/2/02 | Thu 5/2/02 | 100% |
138 | Hopefully not necessary | Cork | 0 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
130 | Get Beamlines online | Byrne | 2 hrs | Tue 5/7/02 | Tue 5/7/02 | 100% |
130 | Get Beamlines online | Hamamoto | 2 hrs | Tue 5/7/02 | Tue 5/7/02 | 100% |
127 | Key enable all beamlines (WITHOUT opening the shutter) | Hamamoto | 72 hrs | Sat 5/4/02 | Tue 5/7/02 | 100% |
127 | Key enable all beamlines (WITHOUT opening the shutter) | Byrne | 36 hrs | Sat 5/4/02 | Tue 5/7/02 | 100% |
132 | Absolute Orbit / bumps | Byrne | 6 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
132 | Absolute Orbit / bumps | Duarte | 6 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
132 | Absolute Orbit / bumps | Beamlines | 6 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
64 | Radiation survey during injection and stored beam | Fairchild | 10 hrs | Tue 4/30/02 | Wed 5/1/02 | 100% |
111 | Temperature Scans main cavities with HOM dampers | Byrd | 12 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
111 | Temperature Scans main cavities with HOM dampers | Kwiatkowski | 12 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
111 | Temperature Scans main cavities with HOM dampers | Barry | 12 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
111 | Temperature Scans main cavities with HOM dampers | Stover | 12 hrs | Sun 5/5/02 | Sun 5/5/02 | 100% |
121 | Initial tests with fast orbit feedback II | Steier | 8 hrs | Mon 5/6/02 | Tue 5/7/02 | 0% |
121 | Initial tests with fast orbit feedback II | Jacobson | 8 hrs | Mon 5/6/02 | Tue 5/7/02 | 0% |
121 | Initial tests with fast orbit feedback II | Domning | 8 hrs | Mon 5/6/02 | Tue 5/7/02 | 0% |
121 | Initial tests with fast orbit feedback II | Scarvie | 8 hrs | Mon 5/6/02 | Tue 5/7/02 | 0% |
121 | Initial tests with fast orbit feedback II | Nadolski | 8 hrs | Mon 5/6/02 | Tue 5/7/02 | 0% |
125 | Initial tests with fast orbit feedback III | Steier | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
125 | Initial tests with fast orbit feedback III | Jacobson | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
125 | Initial tests with fast orbit feedback III | Domning | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
125 | Initial tests with fast orbit feedback III | Scarvie | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
125 | Initial tests with fast orbit feedback III | Nadolski | 4 hrs | Tue 5/7/02 | Tue 5/7/02 | 0% |
107 | Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 Milliamps | Byrd | 6 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
107 | Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 Milliamps | Kwiatkowski | 6 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
107 | Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 Milliamps | Barry | 6 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
107 | Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 Milliamps | Stover | 6 hrs | Sat 5/4/02 | Sat 5/4/02 | 100% |
134 | Reevaluate Beamlines | Byrne | 6 hrs | Wed 5/8/02 | Wed 5/8/02 | 0% |
134 | Reevaluate Beamlines | Duarte | 6 hrs | Wed 5/8/02 | Wed 5/8/02 | 0% |
134 | Reevaluate Beamlines | Beamlines | 6 hrs | Wed 5/8/02 | Wed 5/8/02 | 0% |
1 | Baseline Measurements done (Power Supplies, Orbit, Injection, Coupling, EPU, Control Syetem, …) | Steier | 0 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
1 | Baseline Measurements done (Power Supplies, Orbit, Injection, Coupling, EPU, Control Syetem, …) | Scarvie | 0 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
1 | Baseline Measurements done (Power Supplies, Orbit, Injection, Coupling, EPU, Control Syetem, …) | Nadolski | 0 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
5 | Modify Matlab Software for new PCI control (quads,chicanes,EPU11,scrapers+fast/slow FB) | Scarvie | 24 hrs | Wed 4/3/02 | Fri 4/5/02 | 96% |
5 | Modify Matlab Software for new PCI control (quads,chicanes,EPU11,scrapers+fast/slow FB) | Steier | 24 hrs | Wed 4/3/02 | Fri 4/5/02 | 96% |
9 | Scrapers sector 3 | Scarvie | 6 hrs | Thu 4/4/02 | Thu 4/4/02 | 100% |
9 | Scrapers sector 3 | Steier | 6 hrs | Thu 4/4/02 | Thu 4/4/02 | 100% |
8 | EPU sector 11 (prepare chicanes) | Scarvie | 6 hrs | Thu 4/4/02 | Thu 4/4/02 | 100% |
8 | EPU sector 11 (prepare chicanes) | Steier | 6 hrs | Thu 4/4/02 | Thu 4/4/02 | 100% |
7 | Chicane sector 4 (permanent magnets, hor. Motion, trimcoils) | Scarvie | 12 hrs | Wed 4/3/02 | Thu 4/4/02 | 100% |
7 | Chicane sector 4 (permanent magnets, hor. Motion, trimcoils) | Steier | 12 hrs | Wed 4/3/02 | Thu 4/4/02 | 100% |
6 | QF, QD | Scarvie | 12 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
6 | QF, QD | Steier | 12 hrs | Wed 4/3/02 | Wed 4/3/02 | 100% |
10 | Fast + slow orbit feedback(extended precision DACs) | Scarvie | 24 hrs | Thu 4/4/02 | Fri 4/5/02 | 100% |
10 | Fast + slow orbit feedback(extended precision DACs) | Steier | 24 hrs | Thu 4/4/02 | Fri 4/5/02 | 100% |
91 | Test new scrapers with beam | Thur | 2 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
91 | Test new scrapers with beam | Steier | 2 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
91 | Test new scrapers with beam | Scarvie | 2 hrs | Wed 5/1/02 | Wed 5/1/02 | 100% |
23 | HOM dampers installed | Kwiatkowski | 0 hrs | Thu 4/18/02 | Thu 4/18/02 | 100% |