Superbend Commissioning





Project Start:
Project Finish:
Mon 8/20/01
Thu 10/4/01


Tasks


IDTask NameDurationStartFinishResource Names% Complete
1Baseline Measurements (Power Supply, Orbit, Inj. …) taken0 daysMon 8/20/01Mon 8/20/01 100%
2      
3Work during Shutdown6.67 daysMon 8/20/01Thu 8/30/01 100%
4Write Software (Matlab on Sun) for easy control of new PS3 edaysMon 8/20/01Thu 8/23/01 100%
5Test high level displays for Superbends1.66 edaysThu 8/23/01Fri 8/24/01 100%
6Control System 100% Functional (Linac, booster)0 daysTue 8/28/01Tue 8/28/01 100%
7      
8Check compensation of gradient bend power supply16 ehrsMon 8/27/01Tue 8/28/01 100%
9Check compensation of all Superbend power supplies2 edaysTue 8/28/01Thu 8/30/01 100%
10      
11Finish Shutdown, start Injector1.75 daysTue 8/28/01Fri 8/31/01 100%
12Finish work in LINAC, booster + SR120 daysTue 8/28/01Tue 8/28/01 100%
13Search and secure LINAC, booster + SR128 hrsTue 8/28/01Tue 8/28/01 100%
14Follow comprehensive startup procedure (Linac+booster)8 hrsTue 8/28/01Tue 8/28/01 100%
15Set correct (lower, -12 kHz) rf-frequency0.5 ehrsTue 8/28/01Tue 8/28/01 100%
16Beam Thru Injector to BTS Line1.66 edaysWed 8/29/01Thu 8/30/01 100%
17Beam Thru BTS Line (check for influence of SR12 Superbend)16 hrsThu 8/30/01Fri 8/31/01 100%
18Finish all shutdown work0 daysWed 8/29/01Wed 8/29/01 100%
19      
20 Search & Secure Storage Ring8 hrsWed 8/29/01Wed 8/29/01 100%
21Follow comprehensive startup procedure (storage ring)24 ehrsWed 8/29/01Thu 8/30/01 100%
22      
23Complete Control System 100% Functional 0 daysWed 8/29/01Wed 8/29/01 100%
24Complete Transition to New Controls W/O Beam0 daysWed 8/29/01Wed 8/29/01 100%
25Good Vacuum W/O Beam0 daysWed 8/29/01Wed 8/29/01 100%
26      
27Hardware Checkout W/O Beam0.67 daysThu 8/30/01Fri 8/31/01 100%
28DCCT 0.5 hrsThu 8/30/01Thu 8/30/01 100%
29Scrapers1 hrThu 8/30/01Thu 8/30/01 100%
30Tune Measurement System1 hrThu 8/30/01Thu 8/30/01 100%
31Rf Frequency0.5 hrsThu 8/30/01Thu 8/30/01 100%
32BPM and IDBPM data rates (no beam)0.5 hrsThu 8/30/01Thu 8/30/01 100%
33Shunts2 hrsThu 8/30/01Thu 8/30/01 100%
34Power Supplies (all)0.67 daysThu 8/30/01Fri 8/31/01 100%
35Stability8 hrsThu 8/30/01Thu 8/30/01 100%
36SP-AM8 hrsThu 8/30/01Thu 8/30/01 100%
37Data Rates8 hrsThu 8/30/01Thu 8/30/01 100%
38Ramping8 hrsThu 8/30/01Fri 8/31/01 100%
39Check Power Supply Can Reach Max/Min Current8 hrsThu 8/30/01Fri 8/31/01 100%
40      
41Start storage ring injection (zero dispersion lattice)0.67 daysFri 8/31/01Sat 9/1/01 100%
42Radiation survey during injection and stored beam14 ehrsFri 8/31/01Fri 8/31/01 100%
43Correct first turn orbit4 hrsFri 8/31/01Fri 8/31/01 100%
44Adjust tunes/lattice2 hrsFri 8/31/01Fri 8/31/01 100%
45Tune rf phase - relative energy2 hrsFri 8/31/01Fri 8/31/01 100%
46Initial multi turn optimization/store beam0.33 daysFri 8/31/01Sat 9/1/01 100%
47BPM checkout0.06 daysFri 8/31/01Fri 8/31/01 100%
48Check BPMs Calibrate0.5 hrsFri 8/31/01Fri 8/31/01 100%
49Check Sample Rates0.5 hrsFri 8/31/01Fri 8/31/01 100%
50Measure Noise0.5 hrsFri 8/31/01Fri 8/31/01 100%
51Tune Measurement0.5 hrsFri 8/31/01Fri 8/31/01 100%
52RF Frequency0.5 hrsFri 8/31/01Fri 8/31/01 100%
53Quick setup (orbit, tune, chrom correction)4.5 hrsFri 8/31/01Fri 8/31/01 100%
54Response Matrix Measured1 hrFri 8/31/01Sat 9/1/01 100%
55First Stored Beam in SR0 daysSat 9/1/01Sat 9/1/01 100%
56Scrub With Beam (1.5 GeV, 260 mA)8 ehrsSat 9/1/01Sat 9/1/01 100%
57Analyze response matrix8 ehrsFri 8/31/01Sat 9/1/01 100%
58      
59Continue Checkout and Setup With Beam0.67 daysSat 9/1/01Sun 9/2/01 100%
60Continue Lattice and Orbit Adjustments8 hrsSat 9/1/01Sat 9/1/01 100%
61Initial Measurement Of Orbit Jitter4 hrsSat 9/1/01Sat 9/1/01 100%
62Initial Characterization Of Ramping4 hrsSat 9/1/01Sun 9/2/01 100%
63      
64Scrub With Beam (1.5 GeV, 260 mA)8 ehrsSat 9/1/01Sun 9/2/01 100%
65      
66Ramp to 1.9 Gev0.67 daysSun 9/2/01Mon 9/3/01 50%
67Optimize ramptables8 hrsSun 9/2/01Sun 9/2/01 100%
68Orbit correction during ramp (not necessary!)8 hrsSun 9/2/01Mon 9/3/01 0%
69      
70Shutdown before holiday1 ehrSun 9/2/01Sun 9/2/01 0%
71Startup after Holiday4 ehrsTue 9/4/01Tue 9/4/01 0%
72Scrub With Beam (1.9 GeV, 100 mA)4 ehrsTue 9/4/01Tue 9/4/01 0%
73Sufficiently Good Vacuum For Precision Machine Studies0 daysTue 9/4/01Tue 9/4/01 100%
74Decision Point for Control System (revert to ILCs ?)0 daysTue 9/4/01Tue 9/4/01 0%
75      
76Hardware Checkout With Beam Continued1.92 daysTue 9/4/01Fri 9/7/01 26%
77Tested Orbit Feedback4 hrsTue 9/4/01Tue 9/4/01 0%
78Initial Check of Transverse Multibunch Feedbacks4 hrsTue 9/4/01Tue 9/4/01 100%
79EEBI Tests (Superbends)8 ehrsTue 9/4/01Wed 9/5/01 0%
80EPBI Test 28 ehrsWed 9/5/01Wed 9/5/01 0%
81Initial detailed Machine Setup1.25 daysWed 9/5/01Fri 9/7/01 30%
82Adjust QFAs Using Dispersion2 hrsWed 9/5/01Wed 9/5/01 100%
83Measure Response Matices With and Without Sextupoles2 hrsWed 9/5/01Wed 9/5/01 0%
84Scrubbing8 ehrsWed 9/5/01Wed 9/5/01 0%
85Orbit Motion Measurements3 hrsWed 9/5/01Thu 9/6/01 100%
86Check 3 HC Settings (because of different rf frequency)4 hrsThu 9/6/01Thu 9/6/01 0%
87Initial Check Of Longitudinal Multibunch Feedback2 hrsThu 9/6/01Thu 9/6/01 100%
88Commission new Millmega LFB amplifier6 hrsThu 9/6/01Thu 9/6/01 100%
89Measurement of Beam Stability With Feedback Systems at 400 Milliamps8 ehrsThu 9/6/01Fri 9/7/01 0%
90Radiation Survey at full current8 ehrsThu 9/6/01Fri 9/7/01 0%
91      
92Initial Dynamics studies (zero dispersion)1 dayFri 9/7/01Sat 9/8/01 67%
93On energy dynamics8 hrsFri 9/7/01Fri 9/7/01 100%
94Off energy dynamics8 hrsFri 9/7/01Sat 9/8/01 100%
95Study Of Lifetime Versus Distributed Dispersion8 hrsSat 9/8/01Sat 9/8/01 0%
96      
97Decide about realigning Superbends0 daysFri 9/7/01Fri 9/7/01 100%
98      
99 Beam Based Alignment1.67 daysSat 9/8/01Mon 9/10/01 14%
100Prepare For Beam Based Alignment8 hrsSat 9/8/01Sat 9/8/01 100%
101Find QF and QD Centers16 ehrsSat 9/8/01Sun 9/9/01 0%
102Find QFA+QDA Centers16 ehrsSun 9/9/01Mon 9/10/01 0%
103Find IDPM to Bpm Centers8 ehrsMon 9/10/01Mon 9/10/01 0%
104Establish Golden Orbit Without User Bumps4 hrsMon 9/10/01Mon 9/10/01 0%
105Measure Response Matrix again4 ehrsMon 9/10/01Mon 9/10/01 0%
106      
107Fit Model8 ehrsMon 9/10/01Tue 9/11/01 0%
108Generate Feed Forward Tables8 ehrsMon 9/10/01Tue 9/11/01 0%
109      
110Finite dispersion/ low emittance Lattice2.17 daysTue 9/11/01Fri 9/14/01 0%
111Setup finite dispersion Lattice1 edayTue 9/11/01Wed 9/12/01 0%
112Dynamics studies1 edayWed 9/12/01Thu 9/13/01 0%
113Check for High Beam Loss Levels In Straight Sections4 hrsThu 9/13/01Thu 9/13/01 0%
114Orbit feedback with finite dispersion12 ehrsThu 9/13/01Fri 9/14/01 0%
115Orbit feedback + rf feedback12 ehrsFri 9/14/01Fri 9/14/01 0%
116      
117Operational tests1.75 daysFri 9/14/01Mon 9/17/01 0%
118test RF at higher voltage/beampower8 ehrsFri 9/14/01Fri 9/14/01 0%
119RF direct ampl. Loop (higher energy loss/turn)8 ehrsFri 9/14/01Sat 9/15/01 0%
120Harmonic Cavity optimization (energy loss/coupling/emittance)8 ehrsSat 9/15/01Sat 9/15/01 0%
121Routine high current operation18 ehrsSat 9/15/01Sun 9/16/01 0%
122Check beam energy match with Femtosecond Slicing18 ehrsSat 9/15/01Sun 9/16/01 0%
123Key enable ID beamlines1 edaySat 9/15/01Sun 9/16/01 0%
124Initial check of alignment of ID beamlines1 edaySun 9/16/01Mon 9/17/01 0%
125      
126Decide on whether to keep Superbends0 daysWed 9/19/01Wed 9/19/01 100%
127Decide on exact timing of mini-shutdown0 daysThu 9/13/01Thu 9/13/01 0%
128      
129Mini-Shutdown (3 days) to complete M1 in 8 and carbon filters in 52 daysMon 9/17/01Wed 9/19/01 0%
130Reinstall 8.2 and 8.3 mirrors2.33 edaysMon 9/17/01Wed 9/19/01 0%
131Finish Beamline 5.0 carbon filter work2.33 edaysMon 9/17/01Wed 9/19/01 0%
132Startup after shutdown8 ehrsWed 9/19/01Wed 9/19/01 0%
133      
134Key enable SB beamlines+beamline 58 ehrsWed 9/19/01Thu 9/20/01 0%
135Initial check of alignment of SB beamlines8 ehrsThu 9/20/01Thu 9/20/01 0%
136Radiation survey during first operation of SB beamlines8 ehrsThu 9/20/01Thu 9/20/01 0%
137      
138Detailed Dyamics studies …1.67 daysThu 9/20/01Sun 9/23/01 0%
139Continue dynamics studies8 ehrsThu 9/20/01Fri 9/21/01 0%
140Continue dynamics studies16 ehrsFri 9/21/01Sat 9/22/01 0%
141Continue dynamics studies16 ehrsSat 9/22/01Sun 9/23/01 0%
142      
143Beamline 5 carbon filter scrubbing2 daysThu 9/20/01Sun 9/23/01 0%
144Initial Beamline 5 Scrubbing8 ehrsThu 9/20/01Thu 9/20/01 0%
145Beamline 5 Scrubbing8 ehrsFri 9/21/01Fri 9/21/01 0%
146Beamline 5 Scrubbing8 ehrsSat 9/22/01Sat 9/22/01 0%
147Beamline 5 Scrubbing8 ehrsSun 9/23/01Sun 9/23/01 0%
148      
149Non vital accelerator physics studies 11.33 daysSun 9/23/01Tue 9/25/01 0%
150Initial tests with fast orbit feedback1.66 edaysSun 9/23/01Mon 9/24/01 0%
151Scan Small Gap Vacuum Chambers For Lifetime Changes8 ehrsTue 9/25/01Tue 9/25/01 0%
152      
153Non vital accelerator physics studies 24 daysTue 9/25/01Mon 10/1/01 0%
154Coupling Studies1 edayTue 9/25/01Wed 9/26/01 0%
155Improve tune feed forward1 edayWed 9/26/01Thu 9/27/01 0%
156Incorporate tune feed forward into FF table generation0.5 edaysThu 9/27/01Thu 9/27/01 0%
157generate new FF tables0.5 edaysThu 9/27/01Fri 9/28/01 0%
158Far-IR studies1.67 edaysFri 9/28/01Sun 9/30/01 0%
159Single and Multibunch Stability Studies1 edaySun 9/30/01Mon 10/1/01 0%
160      
161Decide what tests need to be performed with users/inform users0 daysFri 9/28/01Fri 9/28/01 0%
162      
163Key enable all beamlines16 ehrsSun 9/30/01Mon 10/1/01 0%
164      
165Operations tests with beamline scientists3 daysMon 10/1/01Thu 10/4/01 0%
166Overall stability1 edayMon 10/1/01Tue 10/2/01 0%
167Absolute Orbit / bumps1 edayTue 10/2/01Wed 10/3/01 0%
168Emittance / coupling1 edayWed 10/3/01Thu 10/4/01 0%
169      
170Align beamlines 4, 5, 7, 8, 1230.29 daysMon 8/20/01Wed 10/3/01 22%
171Frontends/inside tunnel9 edaysMon 8/20/01Wed 8/29/01 100%
172Outside tunnel17.67 edaysWed 8/29/01Sun 9/16/01 0%
173Redo if necessary based on tests (inside tunnel)2.5 edaysMon 9/17/01Wed 9/19/01 0%
174Redo if necessary based on tests (outside tunnel)9 edaysFri 9/21/01Sun 9/30/01 0%
175Final optimization3 edaysSun 9/30/01Wed 10/3/01 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete