April/May 2002 ALS Startup





Project Start:
Project Finish:
Wed 4/3/02
Thu 5/9/02


Tasks


IDTask NameDurationStartFinishResource Names% Complete
1Baseline Measurements done (Power Supplies, Orbit, Injection, Coupling, EPU, Control Syetem, …)0 daysWed 4/3/02Wed 4/3/02Steier,Scarvie,Nadolski100%
2Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...)0 daysWed 4/3/02Wed 4/3/02Byrd,Barry,Stover,Kwiatkowski100%
3      
4Work during Shutdown23.33 daysWed 4/3/02Fri 4/26/02 89%
5Modify Matlab Software for new PCI control (quads,chicanes,EPU11,scrapers+fast/slow FB)3 daysWed 4/3/02Sat 4/6/02Scarvie,Steier96%
6QF, QD0.5 edaysWed 4/3/02Wed 4/3/02Scarvie,Steier100%
7Chicane sector 4 (permanent magnets, hor. Motion, trimcoils)0.5 edaysWed 4/3/02Thu 4/4/02Scarvie,Steier100%
8EPU sector 11 (prepare chicanes)0.25 edaysThu 4/4/02Thu 4/4/02Scarvie,Steier100%
9Scrapers sector 30.25 edaysThu 4/4/02Thu 4/4/02Scarvie,Steier100%
10Fast + slow orbit feedback(extended precision DACs)1 edayThu 4/4/02Fri 4/5/02Scarvie,Steier100%
11Software summing junctions (QF,QD) … deferred0.5 edaysFri 4/5/02Sat 4/6/02Scarvie,Steier75%
12normal precision IP boards replaced (ADC drift problem correctors)0 daysTue 4/9/02Tue 4/9/02Biocca,Chin,Webber100%
13Extended precision DAC boards installed0 daysTue 4/9/02Tue 4/9/02Biocca,Chin100%
14Check all normal precision IP boards1 edayTue 4/9/02Wed 4/10/02Biocca,Timossi,Scarvie,Steier100%
15Check all extended precision DAC boards2 edaysWed 4/10/02Fri 4/12/02Biocca,Timossi,Jacobson,Scarvie,Steier100%
16Measure open loop transferfunctions of fast FB … deferred3 edaysFri 4/12/02Mon 4/15/02Jacobson,Steier,Domning,Scarvie0%
17Superbends ready for startup0 daysMon 4/22/02Mon 4/22/02Calais100%
18Check out thermal behaviour of Superbends2 edaysMon 4/22/02Wed 4/24/02Calais,Bish,Zbasnik,Steier100%
19Check out Superbend ramping with new coldheads1 edayWed 4/24/02Thu 4/25/02Zbasnik,Steier100%
20Check PCI controls of quadrupole supplies3 edaysMon 4/15/02Thu 4/18/02Biocca,Timossi,Scarvie[50%],Steier100%
21New scrapers installed in sector 30 daysMon 4/15/02Mon 4/15/02Thur100%
22Test scraper controls3 edaysTue 4/16/02Fri 4/19/02Thur,Scarvie[50%]100%
23HOM dampers installed0 daysThu 4/18/02Thu 4/18/02Kwiatkowski100%
24Develop schedule for potential removal …5 edaysTue 4/9/02Sun 4/14/02Kwiatkowski,Plate,Colomb,Julian100%
25High power tests (vacuum conditioning) of HOM dampers3 edaysThu 4/18/02Sun 4/21/02Kwiatkowski100%
26Test control room displays for HOM dampers1 edayThu 4/18/02Fri 4/19/02Timossi,McDonald,Scarvie[50%]100%
27Chicanes installed and ready for testing0 daysFri 4/26/02Fri 4/26/02Marks100%
28Test chicane controls (especially sector 4)8 ehrsFri 4/26/02Fri 4/26/02Biocca,Timossi,Robb,Scarvie100%
29EPU in sector 11 installed and ready for testing0 daysTue 4/23/02Tue 4/23/02Marks100%
30Complete Transition to New Controls W/O Beam0 daysFri 4/26/02Fri 4/26/02Biocca,Timossi,Steier100%
31Control System 100% Functional0 daysFri 4/26/02Fri 4/26/02Biocca,Steier100%
32      
33Finish Shutdown, start Injector2.21 daysFri 4/26/02Mon 4/29/02 100%
34Finish all shutdown work0 daysFri 4/26/02Fri 4/26/02Harkins100%
35Search and secure LINAC, booster + SR2 ehrsFri 4/26/02Fri 4/26/02Operators[200%]100%
36Follow comprehensive startup procedure (Linac+booster)8 ehrsFri 4/26/02Sat 4/27/02Operators[200%]100%
37Follow comprehensive startup procedure (Storage Ring)16 ehrsSat 4/27/02Sat 4/27/02Operators[200%]100%
38Setup Beam Thru Injector and BTS Line16 ehrsSun 4/28/02Mon 4/29/02Byrne100%
39      
40Good Vacuum W/O Beam (Sublimate early enough)0 daysSun 4/28/02Sun 4/28/02Colomb,Operators0%
41      
42Solve vacuum problems straight 114.33 daysFri 4/26/02Tue 4/30/02 100%
43Repare flanges of new vacuum chamber in straight 113.5 edaysFri 4/26/02Mon 4/29/02 100%
44Pump and leak check0.7 edaysMon 4/29/02Tue 4/30/02 100%
45Sublimate all sectors3 ehrsTue 4/30/02Tue 4/30/02 100%
46EPS tests sectors 11+122 ehrsTue 4/30/02Tue 4/30/02 100%
47Startup procedure/search+secure (like after maintenance day)6 ehrsTue 4/30/02Tue 4/30/02 100%
48      
49Hardware Checkout W/O Beam0.17 daysTue 4/30/02Tue 4/30/02 100%
50DCCT 0.2 ehrsTue 4/30/02Tue 4/30/02Physics100%
51Scrapers1 ehrTue 4/30/02Tue 4/30/02Physics100%
52Tune Measurement System0.2 ehrsTue 4/30/02Tue 4/30/02Physics100%
53RF Frequency0.2 ehrsTue 4/30/02Tue 4/30/02Physics100%
54BPM and IDBPM data rates (no beam)0.5 ehrsTue 4/30/02Tue 4/30/02Physics[50%]100%
55Shunts1 ehrTue 4/30/02Tue 4/30/02Physics[50%]100%
56Test all Power Supplies0.17 daysTue 4/30/02Tue 4/30/02 100%
57Stability2 ehrsTue 4/30/02Tue 4/30/02Physics[50%]100%
58SP-AM2 ehrsTue 4/30/02Tue 4/30/02Physics[50%]100%
59Data Rates2 ehrsTue 4/30/02Tue 4/30/02Physics[50%]100%
60Ramping2 ehrsTue 4/30/02Tue 4/30/02Physics100%
61Check Power Supply Can Reach Max/Min Current1 ehrTue 4/30/02Tue 4/30/02Physics100%
62      
63Start storage ring injection (watch HOM damper temperatures)0.42 daysTue 4/30/02Wed 5/1/02 100%
64Radiation survey during injection and stored beam10 ehrsTue 4/30/02Wed 5/1/02Fairchild100%
65Watch temperatures of HOM dampers -> do not overfill ring10 ehrsTue 4/30/02Wed 5/1/02Kwiatkowski,Julian,Baptiste,Physics,Operators100%
66Correct first turn orbit1 ehrTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
67Adjust tunes/lattice1 ehrTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
68Tune rf phase - relative energy0.5 ehrsTue 4/30/02Tue 4/30/02Steier,Byrne100%
69Initial multi turn optimization/store beam0.21 daysTue 4/30/02Tue 4/30/02 100%
70BPM checkout0.03 daysTue 4/30/02Tue 4/30/02 100%
71Check BPMs Calibrate0.2 ehrsTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
72Check Sample Rates0.2 ehrsTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
73Measure Noise0.2 ehrsTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
74Tune Measurement0.2 ehrsTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
75RF Frequency0.1 ehrsTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
76Quick setup (orbit, tune, chrom correction)1 ehrTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
77Response Matrix Measured0.75 ehrsTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
78Measurement Of Orbit Jitter1.5 ehrsTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
79Test Ramping with new controls1 ehrTue 4/30/02Tue 4/30/02Steier,Scarvie,Nadolski100%
80      
81First Stored Beam in SR0 daysTue 4/30/02Tue 4/30/02Steier100%
82Scrub With Beam (1.9 GeV) -> maybe more time needed ? Vacuumwork in sector 11 ? 6 ehrsTue 4/30/02Wed 5/1/02Operators100%
83During Scrubbing: Test Slow Orbit Feedback (with extended precision DACs)6 ehrsTue 4/30/02Wed 5/1/02Steier,Scarvie100%
84Analyze response matrix4 ehrsTue 4/30/02Wed 5/1/02Steier[0%],Nadolski[0%]100%
85Sufficiently Good Vacuum For Precision Machine Studies0 daysWed 5/1/02Wed 5/1/02 100%
86Decision Point for Control System (revert to ILCs ?)0 daysTue 4/30/02Tue 4/30/02Biocca,Steier,Robin100%
87      
88Beam Physics Studies (HOM dampers, instabilities, feedbacks, beam based alignment, orbit, …)4.67 daysWed 5/1/02Sun 5/5/02 100%
89Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures)12 ehrsWed 5/1/02Wed 5/1/02Kwiatkowski,Byrd,Barry,Stover100%
90EPBI Test 24 ehrsWed 5/1/02Wed 5/1/02Byrne,Operators100%
91Test new scrapers with beam2 ehrsWed 5/1/02Wed 5/1/02Thur,Steier,Scarvie100%
92Monitor radiation levels at new location2 ehrsWed 5/1/02Thu 5/2/02Fairchild100%
93Scan aperture in straight 11 (beam bumps+scraper scans)6 ehrsThu 5/2/02Thu 5/2/02Physics,Operators100%
94Test of HOM dampers 2 (different fill patterns and currents)12 ehrsThu 5/2/02Thu 5/2/02Kwiatkowski,Byrd,Barry,Stover100%
95Test chicane magnets in sector 4+114 ehrsThu 5/2/02Thu 5/2/02Physics,Operators100%
96Measure influence of EPU in sector 11 on beam4 ehrsThu 5/2/02Fri 5/3/02Physics,Operators100%
97Measure absolute orbits/coupling2 ehrsFri 5/3/02Fri 5/3/02Nishimura,Nadolski100%
98Prepare For/Test Beam Based Alignment2 ehrsFri 5/3/02Fri 5/3/02Scarvie100%
99Check 3 HC Settings with HOM dampers4 ehrsFri 5/3/02Fri 5/3/02Byrd,deSantis100%
100Study Longitudinal Multibunch Feedback with HOM dampers8 ehrsFri 5/3/02Fri 5/3/02Stover100%
101 Beam Based Alignment0.58 daysFri 5/3/02Sat 5/4/02 100%
102Find QF and QD Centers6 ehrsFri 5/3/02Sat 5/4/02Physics,Operators100%
103Find QFA+QDA Centers5 ehrsSat 5/4/02Sat 5/4/02Physics,Operators100%
104Establish Golden Orbit Without User Bumps2 ehrsSat 5/4/02Sat 5/4/02Physics,Operators100%
105Measure Response Matrix again1 ehrSat 5/4/02Sat 5/4/02Physics,Operators100%
106Study transverse multibunch feedbacks with HOM dampers6 ehrsSat 5/4/02Sat 5/4/02Barry100%
107Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 Milliamps6 ehrsSat 5/4/02Sat 5/4/02Byrd,Kwiatkowski,Barry,Stover100%
108Fit Lattice Model8 ehrsSat 5/4/02Sat 5/4/02Steier,Nadolski100%
109Generate Feed Forward Tables8 ehrsSat 5/4/02Sun 5/5/02Physics,Operators100%
110Test Routine high current operation4 ehrsSun 5/5/02Sun 5/5/02Physics,Operators,Byrne[50%],Byrd100%
111Temperature Scans main cavities with HOM dampers12 ehrsSun 5/5/02Sun 5/5/02Byrd,Kwiatkowski,Barry,Stover100%
112      
113HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 days0 daysThu 5/2/02Thu 5/2/02Byrd,Kwiatkowski,Robin,Steier100%
114HOM dampers decision point #2 (revert back) -> requires 1 day0 daysSun 5/5/02Sun 5/5/02Byrd,Kwiatkowski,Robin,Steier100%
115      
116      
117      
118Non vital Beam Physics Studies (Contingency time for HOM studies)2 daysSun 5/5/02Tue 5/7/02 17%
119Initial tests with fast orbit feedback I8 ehrsSun 5/5/02Mon 5/6/02Steier,Jacobson,Domning,Scarvie,Nadolski0%
120Scan all small gap vacuum chambers for lifetime changes12 ehrsMon 5/6/02Mon 5/6/02Physics,Operators0%
121Initial tests with fast orbit feedback II8 ehrsMon 5/6/02Tue 5/7/02Steier,Jacobson,Domning,Scarvie,Nadolski0%
122Coupling Studies8 ehrsTue 5/7/02Tue 5/7/02Nadolski100%
123Incorporate tune feed forward into FF table generation4 ehrsTue 5/7/02Tue 5/7/02Steier,Scarvie0%
124Improve tune feed forward4 ehrsTue 5/7/02Tue 5/7/02Steier,Scarvie0%
125Initial tests with fast orbit feedback III4 ehrsTue 5/7/02Tue 5/7/02Steier,Jacobson,Domning,Scarvie,Nadolski0%
126      
127Key enable all beamlines (WITHOUT opening the shutter)3 edaysSat 5/4/02Tue 5/7/02Hamamoto,Byrne[50%]100%
128      
129Operations tests with beamline scientists2 daysTue 5/7/02Thu 5/9/02 8%
130Get Beamlines online2 ehrsTue 5/7/02Tue 5/7/02Byrne,Hamamoto100%
131Evaluate Overall Beam Stability/Quality with Beamlines2 ehrsTue 5/7/02Tue 5/7/02Byrne,Beamlines,Byrd,Steier100%
132Absolute Orbit / bumps6 ehrsTue 5/7/02Tue 5/7/02Byrne,Duarte,Beamlines0%
133Align (potentially frontends)12 ehrsTue 5/7/02Wed 5/8/02Byrne,Duarte,Beamlines0%
134Reevaluate Beamlines6 ehrsWed 5/8/02Wed 5/8/02Byrne,Duarte,Beamlines0%
135Fine Tune Beamline Alignment / Routine Operation20 ehrsWed 5/8/02Thu 5/9/02Byrne,Duarte,Beamlines0%
136      
137Beamline 5 carbon filter scrubbing0 daysTue 5/7/02Tue 5/7/02 0%
138Hopefully not necessary0 ehrsTue 5/7/02Tue 5/7/02Cork0%
139      
140Return to user operation8 ehrsThu 5/9/02Thu 5/9/02Byrne,Steier,Robin0%
141      
142Align beamlines as necessary36 daysWed 4/3/02Thu 5/9/02 95%
143Frontends/inside tunnel20 edaysWed 4/3/02Tue 4/23/02Duarte,Byrne,deMarco100%
144Outside tunnel8 edaysTue 4/23/02Wed 5/1/02Duarte,deMarco,Beamlines100%
145Final optimization2 edaysTue 5/7/02Thu 5/9/02Beamlines20%

Resources


IDNameGroupMax UnitsPeak Units
1Byrd 100%100%
2Barry 100%100%
3Stover 100%100%
4Steier 100%200%
5Scarvie 100%200%
6Nadolski 100%100%
7Biocca 100%100%
8Chin 100%0%
9Webber 100%0%
10Timossi 100%100%
11Jacobson 100%100%
12Domning 100%100%
13Calais 100%100%
14Bish 100%100%
15Zbasnik 100%100%
16Thur 100%100%
17Kwiatkowski 100%100%
18McDonald 100%100%
19Marks 100%0%
20Robb 100%100%
21Harkins 100%0%
22Byrne 100%100%
23Operators 200%200%
24Colomb 100%100%
25Fairchild 100%100%
26Physics 300%250%
27Robin 100%100%
28Nishimura 100%100%
29deSantis 100%100%
30Duarte 100%100%
31deMarco 100%100%
32Hamamoto 100%100%
33Beamlines 200%200%
34Cork 100%0%
35Julian 100%100%
36Baptiste 100%100%
37Plate 100%100%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
30Complete Transition to New Controls W/O BeamBiocca0 hrsFri 4/26/02Fri 4/26/02100%
30Complete Transition to New Controls W/O BeamTimossi0 hrsFri 4/26/02Fri 4/26/02100%
30Complete Transition to New Controls W/O BeamSteier0 hrsFri 4/26/02Fri 4/26/02100%
40Good Vacuum W/O Beam (Sublimate early enough)Colomb0 hrsSun 4/28/02Sun 4/28/020%
40Good Vacuum W/O Beam (Sublimate early enough)Operators0 hrsSun 4/28/02Sun 4/28/020%
81First Stored Beam in SRSteier0 hrsTue 4/30/02Tue 4/30/02100%
86Decision Point for Control System (revert to ILCs ?)Biocca0 hrsTue 4/30/02Tue 4/30/02100%
86Decision Point for Control System (revert to ILCs ?)Steier0 hrsTue 4/30/02Tue 4/30/02100%
86Decision Point for Control System (revert to ILCs ?)Robin0 hrsTue 4/30/02Tue 4/30/02100%
50DCCT Physics0.2 hrsTue 4/30/02Tue 4/30/02100%
51ScrapersPhysics1 hrTue 4/30/02Tue 4/30/02100%
52Tune Measurement SystemPhysics0.2 hrsTue 4/30/02Tue 4/30/02100%
53RF FrequencyPhysics0.2 hrsTue 4/30/02Tue 4/30/02100%
55ShuntsPhysics0.5 hrsTue 4/30/02Tue 4/30/02100%
57StabilityPhysics1 hrTue 4/30/02Tue 4/30/02100%
58SP-AMPhysics1 hrTue 4/30/02Tue 4/30/02100%
60RampingPhysics2 hrsTue 4/30/02Tue 4/30/02100%
59Data RatesPhysics1 hrTue 4/30/02Tue 4/30/02100%
61Check Power Supply Can Reach Max/Min CurrentPhysics1 hrTue 4/30/02Tue 4/30/02100%
102Find QF and QD CentersPhysics6 hrsFri 5/3/02Sat 5/4/02100%
102Find QF and QD CentersOperators6 hrsFri 5/3/02Sat 5/4/02100%
78Measurement Of Orbit JitterSteier1.5 hrsTue 4/30/02Tue 4/30/02100%
78Measurement Of Orbit JitterScarvie1.5 hrsTue 4/30/02Tue 4/30/02100%
78Measurement Of Orbit JitterNadolski1.5 hrsTue 4/30/02Tue 4/30/02100%
77Response Matrix MeasuredSteier0.75 hrsTue 4/30/02Tue 4/30/02100%
77Response Matrix MeasuredScarvie0.75 hrsTue 4/30/02Tue 4/30/02100%
77Response Matrix MeasuredNadolski0.75 hrsTue 4/30/02Tue 4/30/02100%
79Test Ramping with new controlsSteier1 hrTue 4/30/02Tue 4/30/02100%
79Test Ramping with new controlsScarvie1 hrTue 4/30/02Tue 4/30/02100%
79Test Ramping with new controlsNadolski1 hrTue 4/30/02Tue 4/30/02100%
106Study transverse multibunch feedbacks with HOM dampersBarry3.65 hrsSat 5/4/02Sat 5/4/02100%
98Prepare For/Test Beam Based AlignmentScarvie2 hrsFri 5/3/02Fri 5/3/02100%
103Find QFA+QDA CentersPhysics5 hrsSat 5/4/02Sat 5/4/02100%
103Find QFA+QDA CentersOperators5 hrsSat 5/4/02Sat 5/4/02100%
104Establish Golden Orbit Without User BumpsPhysics2 hrsSat 5/4/02Sat 5/4/02100%
104Establish Golden Orbit Without User BumpsOperators2 hrsSat 5/4/02Sat 5/4/02100%
105Measure Response Matrix againPhysics1 hrSat 5/4/02Sat 5/4/02100%
105Measure Response Matrix againOperators1 hrSat 5/4/02Sat 5/4/02100%
108Fit Lattice ModelSteier8 hrsSat 5/4/02Sat 5/4/02100%
108Fit Lattice ModelNadolski8 hrsSat 5/4/02Sat 5/4/02100%
109Generate Feed Forward TablesPhysics8 hrsSat 5/4/02Sun 5/5/02100%
109Generate Feed Forward TablesOperators8 hrsSat 5/4/02Sun 5/5/02100%
66Correct first turn orbitSteier1 hrTue 4/30/02Tue 4/30/02100%
66Correct first turn orbitScarvie1 hrTue 4/30/02Tue 4/30/02100%
66Correct first turn orbitNadolski1 hrTue 4/30/02Tue 4/30/02100%
67Adjust tunes/latticeSteier1 hrTue 4/30/02Tue 4/30/02100%
67Adjust tunes/latticeScarvie1 hrTue 4/30/02Tue 4/30/02100%
67Adjust tunes/latticeNadolski1 hrTue 4/30/02Tue 4/30/02100%
68Tune rf phase - relative energySteier0.5 hrsTue 4/30/02Tue 4/30/02100%
68Tune rf phase - relative energyByrne0.5 hrsTue 4/30/02Tue 4/30/02100%
37Follow comprehensive startup procedure (Storage Ring)Operators32 hrsSat 4/27/02Sat 4/27/02100%
34Finish all shutdown workHarkins0 hrsFri 4/26/02Fri 4/26/02100%
71Check BPMs CalibrateSteier0.2 hrsTue 4/30/02Tue 4/30/02100%
71Check BPMs CalibrateScarvie0.2 hrsTue 4/30/02Tue 4/30/02100%
71Check BPMs CalibrateNadolski0.2 hrsTue 4/30/02Tue 4/30/02100%
72Check Sample RatesSteier0.2 hrsTue 4/30/02Tue 4/30/02100%
72Check Sample RatesScarvie0.2 hrsTue 4/30/02Tue 4/30/02100%
72Check Sample RatesNadolski0.2 hrsTue 4/30/02Tue 4/30/02100%
73Measure NoiseSteier0.2 hrsTue 4/30/02Tue 4/30/02100%
73Measure NoiseScarvie0.2 hrsTue 4/30/02Tue 4/30/02100%
73Measure NoiseNadolski0.2 hrsTue 4/30/02Tue 4/30/02100%
74Tune MeasurementSteier0.2 hrsTue 4/30/02Tue 4/30/02100%
74Tune MeasurementScarvie0.2 hrsTue 4/30/02Tue 4/30/02100%
74Tune MeasurementNadolski0.2 hrsTue 4/30/02Tue 4/30/02100%
75RF FrequencySteier0.1 hrsTue 4/30/02Tue 4/30/02100%
75RF FrequencyScarvie0.1 hrsTue 4/30/02Tue 4/30/02100%
75RF FrequencyNadolski0.1 hrsTue 4/30/02Tue 4/30/02100%
76Quick setup (orbit, tune, chrom correction)Steier1 hrTue 4/30/02Tue 4/30/02100%
76Quick setup (orbit, tune, chrom correction)Scarvie1 hrTue 4/30/02Tue 4/30/02100%
76Quick setup (orbit, tune, chrom correction)Nadolski1 hrTue 4/30/02Tue 4/30/02100%
84Analyze response matrixSteier0 hrsTue 4/30/02Tue 4/30/02100%
84Analyze response matrixNadolski0 hrsTue 4/30/02Tue 4/30/02100%
82Scrub With Beam (1.9 GeV) -> maybe more time needed ? Vacuumwork in sector 11 ? Operators6 hrsTue 4/30/02Wed 5/1/02100%
65Watch temperatures of HOM dampers -> do not overfill ringKwiatkowski10 hrsTue 4/30/02Wed 5/1/02100%
65Watch temperatures of HOM dampers -> do not overfill ringJulian10 hrsTue 4/30/02Wed 5/1/02100%
65Watch temperatures of HOM dampers -> do not overfill ringBaptiste10 hrsTue 4/30/02Wed 5/1/02100%
65Watch temperatures of HOM dampers -> do not overfill ringPhysics10 hrsTue 4/30/02Wed 5/1/02100%
65Watch temperatures of HOM dampers -> do not overfill ringOperators10 hrsTue 4/30/02Wed 5/1/02100%
83During Scrubbing: Test Slow Orbit Feedback (with extended precision DACs)Steier6 hrsTue 4/30/02Wed 5/1/02100%
83During Scrubbing: Test Slow Orbit Feedback (with extended precision DACs)Scarvie6 hrsTue 4/30/02Wed 5/1/02100%
131Evaluate Overall Beam Stability/Quality with BeamlinesByrne2 hrsTue 5/7/02Tue 5/7/02100%
131Evaluate Overall Beam Stability/Quality with BeamlinesBeamlines2 hrsTue 5/7/02Tue 5/7/02100%
131Evaluate Overall Beam Stability/Quality with BeamlinesByrd2 hrsTue 5/7/02Tue 5/7/02100%
131Evaluate Overall Beam Stability/Quality with BeamlinesSteier2 hrsTue 5/7/02Tue 5/7/02100%
133Align (potentially frontends)Byrne12 hrsTue 5/7/02Wed 5/8/020%
133Align (potentially frontends)Duarte12 hrsTue 5/7/02Wed 5/8/020%
133Align (potentially frontends)Beamlines12 hrsTue 5/7/02Wed 5/8/020%
90EPBI Test 2Byrne4 hrsWed 5/1/02Wed 5/1/02100%
90EPBI Test 2Operators4 hrsWed 5/1/02Wed 5/1/02100%
20Check PCI controls of quadrupole suppliesBiocca72 hrsMon 4/15/02Thu 4/18/02100%
20Check PCI controls of quadrupole suppliesTimossi72 hrsMon 4/15/02Thu 4/18/02100%
20Check PCI controls of quadrupole suppliesScarvie36 hrsMon 4/15/02Thu 4/18/02100%
20Check PCI controls of quadrupole suppliesSteier72 hrsMon 4/15/02Thu 4/18/02100%
15Check all extended precision DAC boardsBiocca48 hrsWed 4/10/02Fri 4/12/02100%
15Check all extended precision DAC boardsTimossi48 hrsWed 4/10/02Fri 4/12/02100%
15Check all extended precision DAC boardsJacobson48 hrsWed 4/10/02Fri 4/12/02100%
15Check all extended precision DAC boardsScarvie48 hrsWed 4/10/02Fri 4/12/02100%
15Check all extended precision DAC boardsSteier48 hrsWed 4/10/02Fri 4/12/02100%
2Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...)Byrd0 hrsWed 4/3/02Wed 4/3/02100%
2Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...)Barry0 hrsWed 4/3/02Wed 4/3/02100%
2Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...)Stover0 hrsWed 4/3/02Wed 4/3/02100%
2Baseline Measurements done (LFB, TFB, growth rates, mode spectrum beam, mode spectrum main cavities, ...)Kwiatkowski0 hrsWed 4/3/02Wed 4/3/02100%
16Measure open loop transferfunctions of fast FB … deferredJacobson72 hrsFri 4/12/02Mon 4/15/020%
16Measure open loop transferfunctions of fast FB … deferredSteier72 hrsFri 4/12/02Mon 4/15/020%
16Measure open loop transferfunctions of fast FB … deferredDomning72 hrsFri 4/12/02Mon 4/15/020%
16Measure open loop transferfunctions of fast FB … deferredScarvie72 hrsFri 4/12/02Mon 4/15/020%
11Software summing junctions (QF,QD) … deferredScarvie12 hrsFri 4/5/02Sat 4/6/0275%
11Software summing junctions (QF,QD) … deferredSteier12 hrsFri 4/5/02Sat 4/6/0275%
143Frontends/inside tunnelDuarte480 hrsWed 4/3/02Tue 4/23/02100%
143Frontends/inside tunnelByrne480 hrsWed 4/3/02Tue 4/23/02100%
143Frontends/inside tunneldeMarco480 hrsWed 4/3/02Tue 4/23/02100%
144Outside tunnelDuarte192 hrsTue 4/23/02Wed 5/1/02100%
144Outside tunneldeMarco192 hrsTue 4/23/02Wed 5/1/02100%
144Outside tunnelBeamlines192 hrsTue 4/23/02Wed 5/1/02100%
145Final optimizationBeamlines48 hrsTue 5/7/02Thu 5/9/0220%
99Check 3 HC Settings with HOM dampersByrd4 hrsFri 5/3/02Fri 5/3/02100%
99Check 3 HC Settings with HOM dampersdeSantis4 hrsFri 5/3/02Fri 5/3/02100%
35Search and secure LINAC, booster + SROperators4 hrsFri 4/26/02Fri 4/26/02100%
38Setup Beam Thru Injector and BTS LineByrne16 hrsSun 4/28/02Mon 4/29/02100%
54BPM and IDBPM data rates (no beam)Physics0.25 hrsTue 4/30/02Tue 4/30/02100%
100Study Longitudinal Multibunch Feedback with HOM dampersStover8 hrsFri 5/3/02Fri 5/3/02100%
122Coupling StudiesNadolski7 hrsTue 5/7/02Tue 5/7/02100%
124Improve tune feed forwardSteier4 hrsTue 5/7/02Tue 5/7/020%
124Improve tune feed forwardScarvie4 hrsTue 5/7/02Tue 5/7/020%
123Incorporate tune feed forward into FF table generationSteier4 hrsTue 5/7/02Tue 5/7/020%
123Incorporate tune feed forward into FF table generationScarvie4 hrsTue 5/7/02Tue 5/7/020%
110Test Routine high current operationPhysics4 hrsSun 5/5/02Sun 5/5/02100%
110Test Routine high current operationOperators4 hrsSun 5/5/02Sun 5/5/02100%
110Test Routine high current operationByrne2 hrsSun 5/5/02Sun 5/5/02100%
110Test Routine high current operationByrd4 hrsSun 5/5/02Sun 5/5/02100%
119Initial tests with fast orbit feedback ISteier8 hrsSun 5/5/02Mon 5/6/020%
119Initial tests with fast orbit feedback IJacobson8 hrsSun 5/5/02Mon 5/6/020%
119Initial tests with fast orbit feedback IDomning8 hrsSun 5/5/02Mon 5/6/020%
119Initial tests with fast orbit feedback IScarvie8 hrsSun 5/5/02Mon 5/6/020%
119Initial tests with fast orbit feedback INadolski8 hrsSun 5/5/02Mon 5/6/020%
120Scan all small gap vacuum chambers for lifetime changesPhysics8 hrsMon 5/6/02Mon 5/6/020%
120Scan all small gap vacuum chambers for lifetime changesOperators8 hrsMon 5/6/02Mon 5/6/020%
31Control System 100% FunctionalBiocca0 hrsFri 4/26/02Fri 4/26/02100%
31Control System 100% FunctionalSteier0 hrsFri 4/26/02Fri 4/26/02100%
17Superbends ready for startupCalais0 hrsMon 4/22/02Mon 4/22/02100%
18Check out thermal behaviour of SuperbendsCalais48 hrsMon 4/22/02Wed 4/24/02100%
18Check out thermal behaviour of SuperbendsBish48 hrsMon 4/22/02Wed 4/24/02100%
18Check out thermal behaviour of SuperbendsZbasnik48 hrsMon 4/22/02Wed 4/24/02100%
18Check out thermal behaviour of SuperbendsSteier48 hrsMon 4/22/02Wed 4/24/02100%
19Check out Superbend ramping with new coldheadsZbasnik24 hrsWed 4/24/02Thu 4/25/02100%
19Check out Superbend ramping with new coldheadsSteier24 hrsWed 4/24/02Thu 4/25/02100%
12normal precision IP boards replaced (ADC drift problem correctors)Biocca0 hrsTue 4/9/02Tue 4/9/02100%
12normal precision IP boards replaced (ADC drift problem correctors)Chin0 hrsTue 4/9/02Tue 4/9/02100%
12normal precision IP boards replaced (ADC drift problem correctors)Webber0 hrsTue 4/9/02Tue 4/9/02100%
113HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 daysByrd0 hrsThu 5/2/02Thu 5/2/02100%
113HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 daysKwiatkowski0 hrsThu 5/2/02Thu 5/2/02100%
113HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 daysRobin0 hrsThu 5/2/02Thu 5/2/02100%
113HOM dampers decision point #1 (swap bellows against straight spool piece) -> requires 1.5 daysSteier0 hrsThu 5/2/02Thu 5/2/02100%
140Return to user operationByrne8 hrsThu 5/9/02Thu 5/9/020%
140Return to user operationSteier8 hrsThu 5/9/02Thu 5/9/020%
140Return to user operationRobin8 hrsThu 5/9/02Thu 5/9/020%
89Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures)Kwiatkowski12 hrsWed 5/1/02Wed 5/1/02100%
89Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures)Byrd12 hrsWed 5/1/02Wed 5/1/02100%
89Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures)Barry12 hrsWed 5/1/02Wed 5/1/02100%
89Test of HOM dampers 1 (different fill patterns, currents and cavity temperatures)Stover12 hrsWed 5/1/02Wed 5/1/02100%
36Follow comprehensive startup procedure (Linac+booster)Operators16 hrsFri 4/26/02Sat 4/27/02100%
27Chicanes installed and ready for testingMarks0 hrsFri 4/26/02Fri 4/26/02100%
28Test chicane controls (especially sector 4)Biocca8 hrsFri 4/26/02Fri 4/26/02100%
28Test chicane controls (especially sector 4)Timossi8 hrsFri 4/26/02Fri 4/26/02100%
28Test chicane controls (especially sector 4)Robb8 hrsFri 4/26/02Fri 4/26/02100%
28Test chicane controls (especially sector 4)Scarvie8 hrsFri 4/26/02Fri 4/26/02100%
29EPU in sector 11 installed and ready for testingMarks0 hrsTue 4/23/02Tue 4/23/02100%
21New scrapers installed in sector 3Thur0 hrsMon 4/15/02Mon 4/15/02100%
22Test scraper controlsThur72 hrsTue 4/16/02Fri 4/19/02100%
22Test scraper controlsScarvie36 hrsTue 4/16/02Fri 4/19/02100%
24Develop schedule for potential removal …Kwiatkowski120 hrsTue 4/9/02Sun 4/14/02100%
24Develop schedule for potential removal …Plate120 hrsTue 4/9/02Sun 4/14/02100%
24Develop schedule for potential removal …Colomb120 hrsTue 4/9/02Sun 4/14/02100%
24Develop schedule for potential removal …Julian120 hrsTue 4/9/02Sun 4/14/02100%
25High power tests (vacuum conditioning) of HOM dampersKwiatkowski72 hrsThu 4/18/02Sun 4/21/02100%
26Test control room displays for HOM dampersTimossi24 hrsThu 4/18/02Fri 4/19/02100%
26Test control room displays for HOM dampersMcDonald24 hrsThu 4/18/02Fri 4/19/02100%
26Test control room displays for HOM dampersScarvie12 hrsThu 4/18/02Fri 4/19/02100%
13Extended precision DAC boards installedBiocca0 hrsTue 4/9/02Tue 4/9/02100%
13Extended precision DAC boards installedChin0 hrsTue 4/9/02Tue 4/9/02100%
14Check all normal precision IP boardsBiocca24 hrsTue 4/9/02Wed 4/10/02100%
14Check all normal precision IP boardsTimossi24 hrsTue 4/9/02Wed 4/10/02100%
14Check all normal precision IP boardsScarvie24 hrsTue 4/9/02Wed 4/10/02100%
14Check all normal precision IP boardsSteier24 hrsTue 4/9/02Wed 4/10/02100%
135Fine Tune Beamline Alignment / Routine OperationByrne20 hrsWed 5/8/02Thu 5/9/020%
135Fine Tune Beamline Alignment / Routine OperationDuarte20 hrsWed 5/8/02Thu 5/9/020%
135Fine Tune Beamline Alignment / Routine OperationBeamlines20 hrsWed 5/8/02Thu 5/9/020%
97Measure absolute orbits/couplingNishimura2 hrsFri 5/3/02Fri 5/3/02100%
97Measure absolute orbits/couplingNadolski2 hrsFri 5/3/02Fri 5/3/02100%
92Monitor radiation levels at new locationFairchild2 hrsWed 5/1/02Thu 5/2/02100%
93Scan aperture in straight 11 (beam bumps+scraper scans)Physics6 hrsThu 5/2/02Thu 5/2/02100%
93Scan aperture in straight 11 (beam bumps+scraper scans)Operators6 hrsThu 5/2/02Thu 5/2/02100%
95Test chicane magnets in sector 4+11Physics4 hrsThu 5/2/02Thu 5/2/02100%
95Test chicane magnets in sector 4+11Operators4 hrsThu 5/2/02Thu 5/2/02100%
96Measure influence of EPU in sector 11 on beamPhysics4 hrsThu 5/2/02Fri 5/3/02100%
96Measure influence of EPU in sector 11 on beamOperators4 hrsThu 5/2/02Fri 5/3/02100%
114HOM dampers decision point #2 (revert back) -> requires 1 dayByrd0 hrsSun 5/5/02Sun 5/5/02100%
114HOM dampers decision point #2 (revert back) -> requires 1 dayKwiatkowski0 hrsSun 5/5/02Sun 5/5/02100%
114HOM dampers decision point #2 (revert back) -> requires 1 dayRobin0 hrsSun 5/5/02Sun 5/5/02100%
114HOM dampers decision point #2 (revert back) -> requires 1 daySteier0 hrsSun 5/5/02Sun 5/5/02100%
94Test of HOM dampers 2 (different fill patterns and currents)Kwiatkowski12 hrsThu 5/2/02Thu 5/2/02100%
94Test of HOM dampers 2 (different fill patterns and currents)Byrd12 hrsThu 5/2/02Thu 5/2/02100%
94Test of HOM dampers 2 (different fill patterns and currents)Barry12 hrsThu 5/2/02Thu 5/2/02100%
94Test of HOM dampers 2 (different fill patterns and currents)Stover12 hrsThu 5/2/02Thu 5/2/02100%
138Hopefully not necessaryCork0 hrsTue 5/7/02Tue 5/7/020%
130Get Beamlines onlineByrne2 hrsTue 5/7/02Tue 5/7/02100%
130Get Beamlines onlineHamamoto2 hrsTue 5/7/02Tue 5/7/02100%
127Key enable all beamlines (WITHOUT opening the shutter)Hamamoto72 hrsSat 5/4/02Tue 5/7/02100%
127Key enable all beamlines (WITHOUT opening the shutter)Byrne36 hrsSat 5/4/02Tue 5/7/02100%
132Absolute Orbit / bumpsByrne6 hrsTue 5/7/02Tue 5/7/020%
132Absolute Orbit / bumpsDuarte6 hrsTue 5/7/02Tue 5/7/020%
132Absolute Orbit / bumpsBeamlines6 hrsTue 5/7/02Tue 5/7/020%
64Radiation survey during injection and stored beamFairchild10 hrsTue 4/30/02Wed 5/1/02100%
111Temperature Scans main cavities with HOM dampersByrd12 hrsSun 5/5/02Sun 5/5/02100%
111Temperature Scans main cavities with HOM dampersKwiatkowski12 hrsSun 5/5/02Sun 5/5/02100%
111Temperature Scans main cavities with HOM dampersBarry12 hrsSun 5/5/02Sun 5/5/02100%
111Temperature Scans main cavities with HOM dampersStover12 hrsSun 5/5/02Sun 5/5/02100%
121Initial tests with fast orbit feedback IISteier8 hrsMon 5/6/02Tue 5/7/020%
121Initial tests with fast orbit feedback IIJacobson8 hrsMon 5/6/02Tue 5/7/020%
121Initial tests with fast orbit feedback IIDomning8 hrsMon 5/6/02Tue 5/7/020%
121Initial tests with fast orbit feedback IIScarvie8 hrsMon 5/6/02Tue 5/7/020%
121Initial tests with fast orbit feedback IINadolski8 hrsMon 5/6/02Tue 5/7/020%
125Initial tests with fast orbit feedback IIISteier4 hrsTue 5/7/02Tue 5/7/020%
125Initial tests with fast orbit feedback IIIJacobson4 hrsTue 5/7/02Tue 5/7/020%
125Initial tests with fast orbit feedback IIIDomning4 hrsTue 5/7/02Tue 5/7/020%
125Initial tests with fast orbit feedback IIIScarvie4 hrsTue 5/7/02Tue 5/7/020%
125Initial tests with fast orbit feedback IIINadolski4 hrsTue 5/7/02Tue 5/7/020%
107Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 MilliampsByrd6 hrsSat 5/4/02Sat 5/4/02100%
107Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 MilliampsKwiatkowski6 hrsSat 5/4/02Sat 5/4/02100%
107Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 MilliampsBarry6 hrsSat 5/4/02Sat 5/4/02100%
107Measurement of Beam Stability With Feedback Systems and HOM dampers at 400 MilliampsStover6 hrsSat 5/4/02Sat 5/4/02100%
134Reevaluate BeamlinesByrne6 hrsWed 5/8/02Wed 5/8/020%
134Reevaluate BeamlinesDuarte6 hrsWed 5/8/02Wed 5/8/020%
134Reevaluate BeamlinesBeamlines6 hrsWed 5/8/02Wed 5/8/020%
1Baseline Measurements done (Power Supplies, Orbit, Injection, Coupling, EPU, Control Syetem, …)Steier0 hrsWed 4/3/02Wed 4/3/02100%
1Baseline Measurements done (Power Supplies, Orbit, Injection, Coupling, EPU, Control Syetem, …)Scarvie0 hrsWed 4/3/02Wed 4/3/02100%
1Baseline Measurements done (Power Supplies, Orbit, Injection, Coupling, EPU, Control Syetem, …)Nadolski0 hrsWed 4/3/02Wed 4/3/02100%
5Modify Matlab Software for new PCI control (quads,chicanes,EPU11,scrapers+fast/slow FB)Scarvie24 hrsWed 4/3/02Fri 4/5/0296%
5Modify Matlab Software for new PCI control (quads,chicanes,EPU11,scrapers+fast/slow FB)Steier24 hrsWed 4/3/02Fri 4/5/0296%
9Scrapers sector 3Scarvie6 hrsThu 4/4/02Thu 4/4/02100%
9Scrapers sector 3Steier6 hrsThu 4/4/02Thu 4/4/02100%
8EPU sector 11 (prepare chicanes)Scarvie6 hrsThu 4/4/02Thu 4/4/02100%
8EPU sector 11 (prepare chicanes)Steier6 hrsThu 4/4/02Thu 4/4/02100%
7Chicane sector 4 (permanent magnets, hor. Motion, trimcoils)Scarvie12 hrsWed 4/3/02Thu 4/4/02100%
7Chicane sector 4 (permanent magnets, hor. Motion, trimcoils)Steier12 hrsWed 4/3/02Thu 4/4/02100%
6QF, QDScarvie12 hrsWed 4/3/02Wed 4/3/02100%
6QF, QDSteier12 hrsWed 4/3/02Wed 4/3/02100%
10Fast + slow orbit feedback(extended precision DACs)Scarvie24 hrsThu 4/4/02Fri 4/5/02100%
10Fast + slow orbit feedback(extended precision DACs)Steier24 hrsThu 4/4/02Fri 4/5/02100%
91Test new scrapers with beamThur2 hrsWed 5/1/02Wed 5/1/02100%
91Test new scrapers with beamSteier2 hrsWed 5/1/02Wed 5/1/02100%
91Test new scrapers with beamScarvie2 hrsWed 5/1/02Wed 5/1/02100%
23HOM dampers installedKwiatkowski0 hrsThu 4/18/02Thu 4/18/02100%